The steps in order
- Check the rules for the land. Ask the county or city permit office about zoning, setbacks from property lines, flood zones and the permits you need. Have the permits in hand before the home moves.
- Clear. Take out trees, stumps, brush and debris from where the home will stand and from the working area around it. Where footings will go, all organic material such as grass, roots and wood scraps has to come out.
- Grade for drainage. The finished ground must send water away from the home. The federal standard asks for a fall of at least half an inch per foot over the first 10 feet from the foundation. Where the lot does not allow that, drains or swales have to do the job.
- Get the soil ready for footings. The foundation must stand on firm, undisturbed soil or on fill compacted to at least 90 percent of its maximum relative density. The soil's bearing capacity has to be determined before the foundation is built. Every pier needs a footing. In freezing climates ordinary footings go below the frost line, unless a slab or insulated foundation designed for frost is used.
- Make a way in. The truck and the home have to reach the spot. Check gate and driveway width, overhead branches and wires, tight turns, soft ground and any culvert on the route.
- Bring utilities to the site. Water, sewer or septic, and power should be available as the local authority requires before the home arrives.
The figures above are the federal minimums in 24 CFR Part 3285. Its Subpart D covers footings and piers. State installation programs can set stricter figures than these.
Who does what
This varies by state and by seller. Often the buyer hires a local excavation contractor for clearing, grading and the driveway, and a licensed installer builds the foundation and sets the home. Some retailers arrange all of it. Have the contract name who handles each step, and ask your state's manufactured housing agency what an installer must be licensed to do.
Problems to head off
- Water under the home: a low pad that collects rain leads to settling piers and a damp underfloor. Fix the grade before the home comes, not after.
- Loose fill: soil brought in to level a pad has to be compacted. Fill that settles takes the home out of level.
- Flood zones: a home that is wholly or partly in a mapped flood hazard area needs a foundation designed for it. The installer has to check the flood map before installation.
- A blocked route: a driveway that is too narrow or too soft can stop the truck on the day. Measure first, and walk the route with the transporter if you can.
Budgeting for it
Site work depends on your land, so no catalog can price it for you. A flat, cleared lot with utilities at the edge needs little. A wooded slope needs a lot. Our quote builder estimates delivery, set-up and a foundation for your ZIP code. Add written local quotes for clearing, grading, the driveway and utility lines on top. How it works shows the order of the whole purchase.