How one is built
The factory builds the house as box-like sections called modules, with walls, wiring, plumbing and most finishes already in place. Trucks carry the modules to the lot. There, usually with a crane, a crew sets each module on the foundation, joins them, and finishes the roof, siding, interior seams and utility connections.
A good share of the job happens on site. The low-end estimates used by our quote builder show the items involved: $5,000 for crane and crew, $10 per square foot for on-site finishing and $4,000 for a slab foundation. Real figures depend on your lot and your contractor.
Which code applies
Modules follow the building code your state or locality has adopted for houses. The state or local building authority handles approval and inspection, and the process varies by state. The Census Bureau puts the split this way: houses of this kind need a building permit and follow local zoning and building code, while manufactured homes follow the standard set by HUD (Manufactured Housing Survey FAQ).
The federal manufactured housing rules allow for this. Under section 3282.12 of 24 CFR Part 3282, a factory can have a structure excluded from the federal program when it declares that the structure is designed only for a site-built permanent foundation, is not designed to be moved once installed, and is built to a recognized building code.
How to tell it from a manufactured home
- No red federal label. A house built to the federal standard has a red metal label on each section. One built to local code does not. It usually has a state or third-party inspection label instead, and that label differs from state to state.
- Foundation. It is designed for a permanent foundation such as a slab, a crawl space or a basement.
- Chassis. The federal standard requires a permanent chassis. Local code has no such rule: many modules are lifted off a carrier, and some keep a steel frame underneath.
What it means for a buyer
Once the house is on its foundation, lenders and appraisers generally treat it like a site-built one. Each lender sets its own terms, so ask before you commit. You will also need a local building permit and a contractor for the foundation and the finishing work.
Our catalog lists 476 plans of this type, from 358 to 3,633 square feet, in the modular collection. For a side-by-side view of the two building standards, read manufactured vs modular.