What installation covers
The federal installation standards, 24 CFR Part 3285, set the minimum for the first installation of a new home. The manufacturer must supply installation instructions with every home, and the installer works from those. A state may run its own program as long as it protects buyers at least as well.
People also call this work set-up. In order, it is:
- Check the site against the home. The installer confirms that the home was built for the wind, roof load and thermal zones of the place, and finds out whether the lot is in a flood hazard area.
- Prepare the ground. Soil, slope and moisture are dealt with before anything is built.
- Build the foundation. Footings and piers, or another system designed for the home.
- Place and level the home. Each section is moved onto its supports and brought level.
- Join the sections of a double-wide or triple-wide.
- Anchor the home against wind.
- Connect and test the plumbing, gas, ducts and wiring.
- Close up the outside and the inside, then fit skirting if it is used.
Our how it works page shows where this stage falls in the whole purchase.
Preparing the ground
- Soil. Footings must rest on firm, undisturbed soil or on properly compacted fill, with grass and other organic material cleared from under them. The soil's bearing capacity has to be known before the foundation is built, because it sets the size of the footings.
- Drainage. The ground must slope away from the home by at least half an inch per foot for the first ten feet, so that water does not collect underneath.
- Moisture. If the space under the home will be closed in with skirting, polyethylene sheeting at least six mil thick is laid on the ground under the home as a vapor retarder.
- Frost. In freezing climates ordinary footings go below the frost line. The local permit office knows the depth.
- Flood. In a mapped flood hazard area the foundation must be engineered to limit flood damage.
Foundation types
The federal rules for supports are in Subpart D of Part 3285. Piers on footings are the standard method. Other systems are allowed when engineering data supports them.
| Foundation type | What it is | When it is used |
|---|---|---|
| Piers and footings | Columns of concrete block, or adjustable steel or concrete piers, standing on footings under the chassis beams, with ground anchors and straps holding the home down | The usual choice for a manufactured home, on private land and in communities |
| Concrete slab | A concrete pad under the whole home; the piers stand on it and the home is anchored to it | Where local rules or site conditions call for a solid base, and for many modular homes |
| Crawl space | A low perimeter wall of block or poured concrete on footings, with supports inside it and a space you can crawl into | When a lender or a local rule calls for a permanent foundation, and for modular homes |
| Basement | Full-height walls below the home that give a usable lower level | Mainly modular homes; a manufactured home only when the manufacturer has approved a design for it |
A support or anchoring method that differs from the manufacturer's instructions needs either an approved design from the manufacturer, or one prepared by a registered professional engineer or architect and approved by the manufacturer. If a lender is involved, ask what foundation the loan requires before any concrete is poured, because some loans need a permanent one.
How a pier foundation is built
- Blocks. A concrete block used in a pier must be at least 8 by 8 by 16 inches. Blocks are stacked with their hollow cells upright, topped with a solid cap and shimmed tight to the frame.
- Height. Block piers under the frame may be a single stack when they are under 36 inches tall. From 36 to 67 inches they must be double, interlocked stacks. Anything taller must be designed by a registered engineer or architect.
- Clearance. At least 12 inches must remain between the ground and the lowest part of the main frame, under the whole home.
- Position. Where the piers go, and how far apart, comes from the manufacturer's instructions for that floor plan: under the main beams and, where required, along the outside walls and along the join of a multi-section home.
Anchoring against wind
Once the home is blocked and level it must be secured against wind, either with anchor assemblies or with a foundation system that does the same job (Subpart E). The usual method is the ground anchor: a steel rod with a spiral blade that is screwed into the soil and tied to the chassis with steel straps.
- Strength. Each anchor must be rated for a working load of at least 3,150 pounds (24 CFR 3285.402).
- Spacing. How far apart the anchors go depends on the wind zone shown on the home's data plate. In Wind Zones II and III the home must also be anchored along its length.
- Frost. In soil that freezes, anchors go below the frost line unless the foundation is protected from frost.
- Coast. Within 1,500 feet of the coastline in Wind Zones II and III, the stronger requirements shown on the data plate apply.
The data plate is the printed sheet inside the home that states its design zones. Our HUD Code page shows where to find it.
Joining the sections
A double-wide or triple-wide arrives as separate sections that meet along a line installers call the mate-line or marriage line.
- Seal. A gasket supplied by the manufacturer goes along the ceiling, end walls and floor before the sections are brought together, to keep out air, water, insects and rodents.
- Structure. The sections are fastened to each other along the mate-line, inside and out. No gaps may remain between the joined parts once the exterior is closed up.
- Crossovers. Water lines, drains, gas piping, heating ducts and wiring that run in more than one section are connected across the join.
- Close-up. Roofing and siding are completed over the join and made weatherproof. Inside, the shipping braces come out and the wall panels and trim at the seam are fitted.
- Tests. The drains and the gas piping are leak-tested on site, and the electrical system is tested once it is connected.
A single-wide has no join, so this whole stage is skipped.
Who may install and who checks
The installation program is set out in 24 CFR Part 3286. In states where HUD runs it, the installer must hold a HUD installer license, the work must be inspected, and the installer must confirm in writing that the home was installed to the standards. Other states run their own program with their own licensing and inspection rules. Your state's manufactured housing agency can tell you which applies, and the county permit office handles local permits.
Before the sale, the retailer has to give you a separate written disclosure about the installation rules that apply to the home. Keep it with the installation instructions.
What set-up and a pier foundation cost in our quote builder
The quote builder prices this work by the size of the home. These are the low-end estimates used by our quote builder, not quotes:
- Set-up: $2,000 for a single-wide, $4,000 for a double-wide and $6,000 for a triple-wide.
- Pier foundation: $1,000 for a single-wide, $2,000 for a double-wide and $3,000 for a triple-wide.
- Skirting, if you add it: $1,000, $2,000 and $3,000 for the same three sizes.
A modular home is priced differently, because it is lifted into place and finished on site: $5,000 for the crane and crew, $10 per square foot for on-site finishing and $4,000 for a slab foundation, again as low-end estimates used by our quote builder. Manufactured vs modular compares the two kinds of home.
None of these figures covers site clearing, utility connections, permits, or steps and decks. A crawl space, a basement or an engineered slab under a manufactured home is quoted by a local contractor.